Maharashtra Halts Adani’s Tarali Hydropower Project Over Missing Wildlife Clearance

The Maharashtra Forest Department has ordered an immediate halt to construction work on Adani Green Energy Limited’s (AGEL) 1,500 MW Tarali Pumped Storage Project in Satara district over the absence of mandatory prior approval from the National Board for Wildlife (NBWL). This notice has been given on November 13, 2026, and raises many concerns about the legality, wildlife, and cost revision of the project.
This 1,500 MW power plant is situated in the Patan taluka of Satara district and is spread across 150.74 hectares of land covering Nivade, Tondoshi, Kalambe, and Jalu villages. In this power plant, Tarali reservoir shall be used as a lower reservoir, and a new upper reservoir will be built.
Why Has Maharashtra Ordered a Work Halt?
Forest Department informed that the inspection revealed the construction activity taking place without any pre-approval from NBWL. The department asked the company to halt the construction process until all approvals are obtained.
A show cause notice was sent by the department asking the company to give a satisfactory reason within three days as to why the construction took place without wildlife clearance. They were asked to produce statutory clearances, maps of the project site and tree felling permission.
It was further mentioned that not providing a satisfactory reason or non-compliance of the notice would lead to legal action being taken against them.
This is in response to the concerns raised by environmentalists and wildlife authorities about the project’s effects on the ecologically sensitive region of Sahyadri.
Adani Green Says It Has Obtained Other Clearances
However, Adani Green Energy denied the allegation of initiating the construction without obtaining all clearances. According to the statement made by Adani Green Energy on November 16, the project neither requires any forest land nor any designated protected area.
As per AGEL, they had obtained the no forest land certificate in January 2024, and environmental clearance had been granted by the Ministry of Environment, Forest and Climate Change on February 11, 2025, while the Consent to Establish was issued by the Maharashtra Pollution Control Board on April 7, 2025.
It is further reported by AGEL that they had submitted their wildlife clearance proposal to the National Board for Wildlife and that is under consideration.
However, it must be noted that environmental clearance and consent to establish do not necessarily replace the wildlife clearance, if needed..
Project Cost Revision Raises Additional Questions
This project has come under fire due to an important modification in the projected cost associated with it. The projected cost originally was ₹5,675 crore, whereas in September 2026 a company affidavit claimed it was ₹56.75 crore.
This modification will affect the amount of the conservation charge for this project. The relevant charge of 4% will be reduced from ₹227 crore to ₹2.27 crore based on the modified projected cost.
The company has clarified that the ₹56.75 crore was the cost of surveys and investigations, not the project’s total cost.
The ministry of environment of the Union has asked the Maharashtra government to investigate any claims about this project on November 6.
Environmental Compliance Under Scrutiny
Tarali project was opposed by the local residents and environmentalists because of the destruction of the trees and the blast that could happen, thus affecting the whole environment around.
Stoppage of the work does not necessarily mean that the whole project has been canceled. The future of the project will depend on how the company reacts to this situation.
This case emphasizes the significance of carrying out all the environmental and wildlife clearance before the construction process starts.
Aviation Safety, Global Diplomacy, Banking Jobs, Naval Defence & AI Innovation
What Do DGCA’s New Aircraft Engine Inspection Rules Mean?
Explore the updated inspection protocols, understand the new aviation safety requirements, and discover how the changes could strengthen aircraft maintenance and operational safety.
Why Is Israel’s Peace Plan Stance Affecting Political Settlement Efforts?
Understand Israel’s position on the proposed peace plan, explore the key disagreements, and discover why reaching a political settlement remains challenging.
How Can You Apply for SBI Junior Associate Recruitment 2026?
Explore the 7,680 vacancies, check eligibility requirements and important dates, and follow the application process for SBI Junior Associate positions.
What Makes the Indian Navy’s New Patrol Vessel ‘Shruti’ Important?
Discover the key features of the next-generation patrol vessel, explore its operational role, and understand how it could strengthen India’s maritime surveillance capabilities.
What Will IBM and CHRIST University’s AI Innovation Center Offer?
Explore the new Bengaluru-based partnership, discover its focus on advanced AI innovation, and understand what it could mean for research, education, and industry collaboration.